Uganda Pays Shs373B for Rail Land, but Shs472B Still Awaits Payment

Key Highlights

  • The government has paid 7,721 people affected by the railway, but another 5,225 remain due compensation before full construction can proceed.
  • Only 2,108 of the 3,536 acres required for the 272-kilometre Malaba-Kampala corridor have been acquired so far.
  • Uganda now targets January 2027 for financial close on a KSh406 billion (€2.70 billion) project that has yet to enter full construction.

Uganda has paid Shs373.07 billion (about KSh13.2 billion) to 7,721 people affected by the planned Malaba-Kampala Standard Gauge Railway, but a larger compensation bill remains outstanding as the government prepares to move the project towards full construction.

Officials at an earlier Malaba-Kampala SGR project ceremony stand beside a rendering of the planned Eastern Route.
File photograph from an earlier Malaba-Kampala SGR project ceremony, where officials stood beside a rendering of the planned Eastern Route.Photo Credit: New Vision

A further Shs472.45 billion (about KSh16.7 billion) is still due to 5,225 project-affected people, according to Works and Transport Minister Fred Byamukama's statement to Parliament on 17 November.

The payments have enabled the government to take possession of 2,108 acres out of the 3,536 acres required for the 272-kilometre railway corridor, according to the Parliament of Uganda's project update.

The figures show progress on land acquisition, but they also underline why the project has not yet moved into major construction. The contractor has completed preparatory work under a limited notice to proceed, while the full financing package and formal authorisation for construction remain outstanding.

The Kenyan shilling equivalents in this article are approximate conversions using the Bank of Uganda's 16 November opening exchange-rate card. They are provided for comparison, not as transaction rates.

Compensation has cleared only part of the route

The Malaba-Kampala line is intended to connect Uganda's capital and eastern border with Kenya's Standard Gauge Railway and the Port of Mombasa. The route is 272 kilometres long and is a key part of the Northern Corridor, which carries imports and exports between the coast and landlocked economies in East Africa.

Parliament was told that 12,946 people are affected by the project. Of these, 7,721 had been compensated by 17 November, leaving 5,225 still waiting. The government has acquired about 60 per cent of the required land by area, based on the 2,108 acres secured against a total requirement of 3,536 acres.

The most advanced stretch is between Malaba and Mayuge, where the minister said about 98 per cent of a continuous corridor had been acquired. That gives the contractor approximately 130 kilometres of uninterrupted land on which it can begin work once the remaining conditions are met.

The minister said compensation and acquisition were continuing, with priority being given to sections considered critical to construction. The outstanding Shs472.45 billion is not a minor balance: using the Bank of Uganda's 16 November rate card, it is approximately KSh16.7 billion, compared with about KSh13.2 billion already paid.

The figures also need to be read carefully. Acquiring a continuous section of land does not mean the full route is ready, and payment to most affected people by count does not mean the compensation process is complete.

Preparatory work is complete, but full construction is still waiting

The government issued a KSh11.3 billion (€75 million) limited notice to proceed to Turkish contractor Yapı Merkezi to carry out essential preparatory activities while it worked to secure financing for the main construction contract.

According to the minister's statement, the limited notice to proceed began on 14 May 2025 and was completed in October 2026. Its scope included surveys, geotechnical investigations and the procurement of essential equipment, including earth-moving machinery.

Byamukama told Parliament that these activities had reduced technical uncertainty and established capacity for a transition to full construction. He was also clear that the limited notice to proceed was only a preparatory arrangement. It did not authorise the contractor to proceed with the full railway works.

Reuters reported on 18 November that the government is targeting financial close in January 2027 for the KSh406 billion (€2.70 billion) project.

The minister told Reuters that major works would begin after financial close and the government's green light to the contractor, rather than immediately after the preparatory contract ended. The Reuters report also says Citibank is helping Uganda mobilise the wider financing.

The Islamic Development Bank has already approved KSh97.8 billion (€650.75 million) for the project, Reuters reported. That approval is an important financing component, but it should not be mistaken for confirmation that the entire project cost has been secured.

Yapı Merkezi is expected to implement the railway over four years from the point at which it receives the green light to begin major works. That means the January 2027 target is a financing milestone, not a construction-completion date.

Land disputes and climate safeguards remain part of the project

The parliamentary debate also exposed concerns beyond the headline compensation totals. Shadow Works Minister Asinansi Nyakato questioned whether the project had adequately budgeted for climate risks and asked the government to clarify the treatment of affected residents.

Byamukama said Shs11 billion, approximately KSh389 million at the same indicative exchange rate, had been earmarked for environmental protection and could be increased if necessary. He also said demolitions raised by lawmakers related to structures found within the gazetted railway reserve, and that boundary-opening exercises would be carried out where the corridor was disputed.

Those explanations remain the government's position. The debate shows that the route still requires careful management of compensation, land boundaries and environmental safeguards as construction moves forward.

The project is also part of a wider regional transport ambition. Reuters reported that Uganda is at an early stage of planning a further 1,425 kilometres of railway extensions towards the north and southwest, with the aim of connecting to South Sudan, the Democratic Republic of Congo and Rwanda. Those extensions are plans under development, not part of the 272-kilometre Malaba-Kampala contract now awaiting full financial close.

What the January financing target will decide

The immediate test is whether Uganda can complete the financing arrangements and issue the full notice to proceed. Until then, the completed surveys, geotechnical work and equipment procurement remain preparation rather than evidence that the railway's main construction phase has begun.

For regional traders, the line's value will depend on whether it eventually offers a reliable rail connection into Kenya and onward to Mombasa. The Kenyan side of that ambition is also facing financing and accountability questions.

Mwenendo has previously examined the KSh651 billion cost of Kenya's next SGR phase and the procurement rules governing major railway contracts.

The January 2027 target therefore matters, but it is not a guarantee. Uganda still has to complete financing, continue compensation, resolve disputed sections of the route and issue the formal instruction that allows major works to start.

#Uganda
#Standard Gauge Railway
#Northern Corridor
#Yapı Merkezi
#Kenya
#Mombasa Port
#rail infrastructure
#compensation

In Summary

Who is responsible for the railway project?
Uganda's Ministry of Works and Transport is overseeing the project, with Turkish contractor Yapı Merkezi responsible for construction under the contract.
How much compensation remains unpaid?
The government says Shs472.45 billion, approximately KSh16.7 billion using the Bank of Uganda's 16 November rate card, remains due to 5,225 project-affected people.
When could full construction begin?
Uganda is targeting financial close in January 2027. Major construction would follow only after financing is completed and a full notice to proceed is issued.
Where will the railway run?
The 272-kilometre Eastern Route will connect Malaba on the Kenyan border to Kampala and link Uganda to Kenya's railway network and the Port of Mombasa.
Why does the project matter for trade?
It is intended to provide landlocked Uganda with a rail connection to Kenya's network and Mombasa, improving access to regional and international markets.
What work has already been completed?
A €75 million limited notice to proceed covered surveys, geotechnical investigations and procurement of essential equipment. It was completed in October 2026, but did not authorise full construction.
Rironi-Naivasha Road: Chirchir Promises One Kilometre a Day After Missing October Deadline

Up next

african-economy

Rironi-Naivasha Road: Chirchir Promises One Kilometre a Day After Missing October Deadline

Transport Cabinet Secretary Davis Chirchir says contractors on the Rironi-Naivasha highway will now aim to lay one kilometre of road a day.

Read next story

More from african-economy

See all

Latest from Mwenendo