19 November 2026· By Mwenendo

The Housing Gap: Kenya Spent KSh122B but Handed Over Only 1,836 Homes

Key Highlights

  • Kenya spent KSh122.18 billion on affordable housing in FY2025/26, but the Controller of Budget recorded only 1,836 handovers.
  • The President's wider pipeline figure counts homes at different stages, not completed or occupied units.
  • The gap matters to taxpayers and applicants because high spending has not yet produced matching handovers.

Kenya spent KSh122.18 billion on its affordable housing programme in the 2025/26 financial year but completed and handed over 1,836 homes, according to the Controller of Budget's national budget review.

Fictional Kenyan construction supervisor and workers reviewing progress at a partially completed affordable housing site.
Affordable housing apartments at a Kenyan Government housing development. File photograph.Photo Credit: State Department of Housing and Urban Development

The report shows that spending absorbed almost the entire allocation, while physical progress remained below the programme's annual target.

The figures give important context to President William Ruto's 18 November 2026 State of the Nation Address, in which he said more than 313,000 homes were at different stages of construction. The two sets of figures describe different stages and reporting periods. A project pipeline is not the same as a completed or occupied home. The President's figures are set out in Parliament's official account of the address.

Spending reached 99 per cent of the allocation

The affordable housing sub-programme had a revised allocation of KSh124 billion for FY2025/26. The Controller of Budget recorded expenditure of KSh122.18 billion, equivalent to about 99 per cent absorption.

Development expenditure accounted for KSh120.18 billion, while KSh2 billion went to recurrent costs. The spending rate was high, but the report's physical-progress measure shows that the programme did not meet its annual implementation target.

The Government had set a target of 52 per cent completion of works across 217,654 housing units by 30 June 2026. The Controller of Budget reported physical progress of 24.5 per cent, a shortfall of 27.5 percentage points against that annual target.

Only 1,836 affordable homes were handed over

The report recorded 1,836 affordable housing units completed and handed over during the financial year. Another 1,380 units were substantially complete but still awaiting handover.

A further 103,251 units were under construction. Another 65,649 were at stages ranging from procurement and contract signing to site handover and preliminary works. Those categories explain why the Government can report a large pipeline without having an equivalent number of finished homes ready for occupation.

The Controller of Budget's report also recorded cumulative expenditure of KSh188.36 billion on the Affordable Housing Fund project by June 2026, against a total estimated project value of KSh1.758 trillion. The project implementation table placed the fund at about 15 per cent completion.

The separate social housing programme reported 4,536 units completed and handed over against a target of 80,909. These social housing units should not be merged with the affordable housing sub-programme's 1,836 handovers.

What the 313,000-home figure means

In his State of the Nation Address, Ruto said more than 313,000 homes were at various stages of construction. He also cited 1.37 million registrations on the Boma Yangu platform and more than 18,000 households allocated homes.

Those are three different measures: units in a construction pipeline, people registered on a platform and households allocated homes. None is a count of homes completed and occupied. The address did not provide a stage-by-stage reconciliation showing how the 313,000 units are divided between procurement, construction, completion, handover and occupation.

The Controller of Budget's June report provides a dated programme-level breakdown, including units under construction and units awaiting handover. It does not cover every housing project that may be included in the President's wider 313,000 figure. The numbers should therefore be read together, not treated as directly interchangeable.

The gap between money spent and homes delivered

The main question raised by the review is how the programme converted its budget into completed homes. Spending 99 per cent of an allocation means the money was recorded as spent; it does not show that the intended physical output was completed.

For contractors, suppliers and building-material companies, project progress affects payment schedules, orders and employment. For households, the important measures are completed units, transparent allocation, prices, eligibility, handover dates and actual occupancy.

The report's spending and physical-progress figures leave a clear need for project-level reconciliation. Publishing the value of work certified, payments made to contractors, units handed over and actual occupancy by location would allow the public to see where the gap between expenditure and delivery is occurring.

The Government should also publish a consistent monthly dashboard that separates homes announced, under procurement, under construction, substantially complete, handed over and occupied. That would allow the public to compare the 313,000-unit pipeline with actual delivery without confusing progress at one stage with completion.

June handovers will provide the next test

The next test is the FY2026/27 implementation report. It should show whether the projects that were substantially complete in June have since been handed over, whether the 103,251 units under construction have advanced, and whether new procurement has translated into additional completed homes.

The National Infrastructure Fund is part of the wider financing discussion around the administration's long-term investment agenda. Mwenendo has also examined the evidence behind Ruto's maize, health and jobs claims.

#Kenya affordable housing
#Controller of Budget
#Housing Levy
#Public spending
#Construction
#Ruto State of the Nation
#editor-placed

In Summary

How much did Kenya spend on affordable housing in FY2025/26?
KSh122.18B against a revised allocation of KSh124B, according to the Controller of Budget.
How many affordable homes were handed over?
The programme recorded 1,836 completed and handed-over homes during the financial year. Another 1,380 were substantially complete but awaiting handover.
How did physical progress compare with the target?
Physical progress was 24.5% against a 52% target across 217,654 units by 30 June 2026.
What does the spending gap mean for taxpayers?
KSh122.18B was recorded as spent, but only 1,836 affordable homes were handed over. The report covers a wider pipeline, so it does not support a reliable per-home cost calculation.
Does the 313,000-home figure mean completed houses?
No. It refers to homes at different stages of construction, not units completed and handed over to residents.
What evidence should be checked next?
Handover records, completion certificates, occupancy data, county-level delivery and the spending tied to each completed unit.
A KSh1.23T Gap: Kenya's Final Budget Policy Statement Sets Spending at KSh5.24T

Up next

african-economy

A KSh1.23T Gap: Kenya's Final Budget Policy Statement Sets Spending at KSh5.24T

Kenya's 2027/28 budget narrows the deficit as a share of GDP, but the cash financing requirement still rises by KSh83.7 billion.

Read next story

More from african-economy

See all

Latest from Mwenendo