A New Power Test: ECOWAS and World Bank Review KSh20.8 Billion Electricity ProjectA New Power Test: ECOWAS and World Bank Review KSh20.8 Billion Electricity Project
Key Highlights
- ECOWAS and the World Bank are reviewing a KSh20.8 billion electricity project targeting 202,000 connections in Togo and The Gambia.
ECOWAS and the World Bank have begun a five-day review of a KSh20.8 billion electricity project in Togo and The Gambia, with the next test being whether approved financing turns into household connections, renewable capacity and reliable power.
The project targets 1,800 localities
The Regional Access Increase and Sustainable Energy Project, known as RAISE, received KSh20.8 billion (US$160 million) in World Bank financing in June 2026. The conversion uses a 19 November mid-market rate of KSh130.05 per US dollar, published by Wise.
The project is part of the wider West Africa Regional Electricity Market Programme, which aims to improve power access and cross-border energy integration.
The project targets electricity connections in 1,800 localities, 202,000 household connections and the facilitation of 242 megawatts of renewable energy generation capacity, according to ECOWAS's 17 November project update. The World Bank estimates that about one million people could gain access to electricity if the programme delivers its planned connections.
The World Bank's approval announcement also models labour-income gains equivalent to about 11,700 jobs annually, including 2,500 in The Gambia and 9,200 in Togo. These are estimated economic effects, not jobs already created or guaranteed positions.
The project is designed to expand and densify distribution networks, lower connection costs and support renewable generation, particularly in rural and peri-urban communities.
The money is approved, but delivery must be tracked
The World Bank approved the KSh20.8 billion (US$160 million) financing on 24 June 2026. ECOWAS says the project became effective on 29 October and that a KSh1.3 billion (US$10 million) grant agreement was signed in July to support regional coordination and implementation. The announcement does not explain whether that grant is included in the KSh20.8 billion headline financing, so the figures should not be added together without a formal breakdown.
The World Bank's finance portal lists a KSh6.5 billion (US$50 million) grant for The Gambia's component as effective. As at 31 October, it showed KSh6.4 billion (US$49.5 million) still available and no disbursement recorded. That status is a useful early checkpoint, but it applies to The Gambia's component, not necessarily every part of the wider regional project.
The distinction matters. Board approval is not the same as money being released, contracts being signed, equipment being installed or homes receiving electricity. The current implementation mission is reviewing procurement, financial management, environmental and social safeguards, national implementation arrangements and the 2027 annual work plan and budget.
What reliable power could change for households and businesses
The two countries face high generation costs, limited network infrastructure and affordability barriers, particularly outside major towns. The World Bank says the project is intended to address those constraints by extending and strengthening distribution networks, lowering connection costs and enabling renewable energy development.
For households, a connection can improve access to lighting, refrigeration, communications and essential services. For small businesses, reliable electricity can reduce dependence on diesel generators, protect stock, extend operating hours and make machinery more viable. Agro-processors and digital-service firms could also benefit if the network upgrades reach the communities and business districts that need them.
The wider economic benefit depends on affordability as well as access. A household may be connected but still unable to use electricity regularly if connection charges, tariffs or supply interruptions remain prohibitive. The project documents therefore need to be judged against actual connections, service reliability, household costs and renewable capacity brought into operation.
The World Bank says the project could be completed within three to four years. That is an implementation expectation, not a guarantee. The Gambia's project record lists a closing date of 30 June 2031, leaving room for a longer implementation period if procurement or construction takes more time.
The next test is what the mission puts on record
The 16 to 20 November mission in Abuja is reviewing the 2027 work plan and budget, safeguards, regional procurement, financial management and national procurement in Togo and The Gambia. Its outcome should provide a clearer timetable for the first contracts, network works, renewable-energy investments and household connections.
The next public updates should show how much of the financing has been disbursed, which procurement packages have been awarded, how many localities have been reached and whether the planned 242 megawatts of renewable capacity is being developed or merely prepared. The governments and ECOWAS should also explain how connection costs will be managed for lower-income households.
For African businesses, the project is a reminder that regional energy integration is not only about building generation capacity. Distribution networks, affordable connections, transparent procurement and dependable service determine whether investment reaches factories, farms, shops and households.
Mwenendo has also covered the shift towards lower-carbon industrial investment in the African Development Bank-backed cement project in Ivory Coast. The RAISE project faces a similar test: financing must translate into infrastructure that works and measurable economic benefits.
In Summary
- What is the RAISE project?
- A KSh20.8 billion (US$160 million) World Bank-backed programme to expand electricity access and support renewable generation in Togo and The Gambia.
- Where will the project operate?
- In Togo and The Gambia, with regional coordination through ECOWAS.
- What does it aim to deliver?
- Connections in 1,800 localities, 202,000 household connections and support for 242MW of renewable generation capacity.
- What is happening now?
- An ECOWAS-World Bank implementation support mission is reviewing procurement, safeguards, financial management and the 2027 work plan from 16 to 20 November 2026.
- What should readers watch?
- Actual disbursements, procurement awards, household connections, renewable capacity and the cost of connecting lower-income households.