17 November 2026· By Mwenendo

Guinea Grants 15-Year Mining Permits for PDI Gold's Bankan and Mansounia

Key Highlights

  • Guinea has granted PDI Gold two 15-year exploitation permits, clearing key regulatory hurdles for the Bankan development and Mansounia mining.
  • Bankan's developer now plans to accelerate procurement and engineering, while its first-gold target remains mid-2028.
  • The permits carry a 15 per cent state interest, but construction, capital costs and the production timetable still need to be delivered.

Guinea has granted PDI Gold 15-year exploitation permits for its Bankan project and the Mansounia deposit at the existing Kiniéro mine, clearing the key regulatory approvals the company says it needed to move both developments forward.

PDI Gold field technicians examine drill-core samples from the Bankan project in Guinea.
Field technicians examine drill-core samples during work at the Bankan Gold Project in Guinea.Photo Credit: PDI Gold

PDI Gold announced the permits on 17 November after the Guinean government issued the relevant decrees on 16 November. In its announcement to the Australian Securities Exchange, the company says the Bankan permit allows it to accelerate procurement, detailed engineering and compensation work before construction begins.

The Mansounia permits are intended to allow mining at a deposit that could improve the output and cost profile of the operating Kiniéro mine.

The approvals strengthen PDI's position in Guinea, but they do not mean Bankan is already under construction or producing gold. The company is still preparing an updated execution schedule, capital estimate and production profile, which it expects to release in early 2027.

Two permits, one larger production plan

PDI says the Bankan Exploitation Permit is held by its subsidiary Hamana Gold SA, covers 98.6 square kilometres and has an initial term of 15 years. The Mansounia permits are held by Sycamore Mine Guinee SAU and also have initial terms of 15 years.

The company says Guinea is entitled to a 15 per cent interest in the exploitation permits under the country's Mining Code. The permits are therefore not simply a transfer of control to the developer; they provide the legal basis for development while preserving the state's statutory participation.

Bankan is the larger growth project. PDI's June 2025 definitive feasibility study set out a planned production rate of about 250,000 ounces of gold a year over an initial 12-year mine life. The study estimated upfront capital costs of about KSh60.18 billion (US$463 million), using the Central Bank of Kenya's indicative rate of KSh129.98 per dollar published on 17 November 2026.

That cost estimate comes from the 2025 feasibility study, not a new construction budget. PDI says it does not currently anticipate an increase to that figure, but is completing an optimised estimate and schedule for release in early 2027. The company has also said it is pursuing opportunities to reduce capital costs.

Bankan moves towards construction

PDI's announcement says the permits are the final key regulatory approvals required before construction can start at Bankan. The board has authorised the company to accelerate procurement, detailed engineering and compensation activities so that construction can begin as soon as practicable.

The project has a reported probable ore reserve of 2.95 million ounces. The feasibility study's production forecast remains about 250,000 ounces a year over 12 years, with first gold targeted for mid-2028. That date is a company target and remains dependent on construction execution, procurement, financing, infrastructure, environmental and social work and other operating risks.

PDI estimates that Bankan could create about 2,000 construction jobs and approximately 1,000 ongoing operating jobs. Those are projections from the company, not confirmed employment figures. The actual local benefit will depend on how much work goes to Guinean employees and suppliers and how the project manages its relationship with host communities.

Mansounia could lift the existing Kiniéro operation

Mansounia is different from Bankan because it forms part of PDI's existing Kiniéro Gold Mine. The company describes the deposit as near-surface and says its grade-control drilling and initial pit designs have already been completed. It plans to begin preparations for mining as soon as practicable.

PDI reports that Kiniéro poured its first gold in December 2025 and reached commercial production in February 2026. At 31 October 2026, the company said 662 Guinean nationals were directly employed at the operation and a further 1,417 were working through local contractors. It said Guinean nationals represented about 91.3 per cent of all people employed by the mine.

Mansounia could allow PDI to use the existing mine's infrastructure and workforce more intensively. The company says the deposit offers an opportunity to improve Kiniéro's near-term production and cost profile, but it has not provided a new production schedule in the permit announcement.

Guinea's mining opportunity still carries execution risks

The permits arrive as Guinea seeks to attract more mining investment and retain a larger share of value from its mineral resources. The country has also introduced local-refining requirements for gold exports, a policy change that has created operational questions for some producers, as covered in Mwenendo's report on Guinea's gold-export bottleneck.

PDI's permit announcement does not say that the new approvals resolve those wider export arrangements.

The immediate milestone is regulatory. The next tests are whether PDI can complete the remaining engineering and compensation work, secure the capital and contractors required, manage local and environmental obligations and keep the mid-2028 first-gold target within reach.

For Guinea, the projects could bring investment, jobs, royalties, taxes and supplier opportunities. For PDI, the permits move Bankan and Mansounia closer to development, but the promised production and economic benefits will depend on what happens after the approvals.

#PDI Gold
#Guinea mining
#Bankan Gold Project
#Kiniéro Gold Mine
#Gold production

In Summary

What permits did Guinea grant?
Two 15-year exploitation permits covering PDI Gold's Bankan project and the Mansounia deposit at its existing Kiniéro operation.
When could Bankan produce its first gold?
PDI's current target is mid-2028, subject to construction, procurement, financing and other execution risks.
What does Guinea receive?
The company says the government is entitled to a 15 per cent interest in the exploitation permits under the Mining Code.
How large is the Bankan project?
PDI's 2025 feasibility study envisages about 250,000 ounces a year over 12 years, with estimated upfront capital of KSh60.18 billion.
Guinea Gold Export Rules Leave Producers Holding Bullion as Refinery Ramps Up

Up next

african-business

Guinea Gold Export Rules Leave Producers Holding Bullion as Refinery Ramps Up

Guinea's local-refining rules are being tested as miners report accumulating bullion and delayed export shipments.

Read next story

More from african-business

See all

Latest from Mwenendo