FirstPower Plans KSh5.07B Network Investment for Anambra Through 2029

Key Highlights

  • FirstPower plans KSh5.07B (₦53.3B, about US$39M) in network upgrades for Anambra between 2027 and 2029.
  • The company also outlined embedded-generation partnerships and power-purchase talks, but those megawatts are not yet commissioned supply.
  • Businesses will need to watch project funding, construction dates and regulatory checks before expecting more reliable electricity.

FirstPower Electricity Distribution Company plans to invest ₦53.3 billion in Anambra's electricity network between 2027 and 2029, a programme worth about KSh5.07 billion or US$39 million. The commitment could strengthen distribution infrastructure in a state whose governor says electricity supply remains far below what businesses and households need.

FirstPower Plans KSh5.07B Network Investment for Anambra Through 2029

The investment plan was announced by Emeka Offor, chairman of Enugu Electricity Distribution Company, at the Anambra State Electricity Market Investment Roundtable in Awka. THISDAY reported that the programme includes ₦13.3 billion for priority network projects in 2027 and a further ₦40 billion planned for 2028 and 2029.

The Kenyan-shilling equivalent uses the Central Bank of Kenya's indicative rate of KSh129.96 to the US dollar published on 12 November. The naira and dollar figures were reported at the investment forum.

What the money is meant to fund

FirstPower is the EEDC subsidiary responsible for electricity distribution in Anambra. Offor said the planned investment would strengthen distribution infrastructure, improve metering, increase network capacity and make electricity supply more reliable.

The first tranche is ₦13.3 billion in 2027, followed by ₦40 billion over the next two years. The announcement does not provide a feeder-by-feeder project list, procurement contracts or commissioning dates, so the full delivery schedule remains to be seen.

For businesses, distribution upgrades matter because power generated somewhere in the system still has to reach factories, shops and homes through working substations, transformers, feeders and metre. More network capacity can reduce bottlenecks, but it does not create electricity where there is not enough generation.

Anambra's supply gap

Governor Chukwuma Soludo told the roundtable that Anambra needs about 1,000 megawatts to support its commercial and industrial ambitions but currently receives roughly 102MW to 120MW from the national grid, according to reports by The Sun and The Business Times

That gap is the reason the company is pursuing both network investment and additional power supply. Anambra's manufacturers and traders need dependable electricity for production, refrigeration, machinery, lighting and digital services. Where supply is unreliable, businesses may have to rely on generators or reduce operating hours, adding costs that are difficult to absorb.

The generation pipeline is at different stages

FirstPower said it was finalising arrangements with generation and renewable energy companies for about 205MW of additional capacity. It also described a 55MW power-purchase agreement under discussion and a memorandum of understanding with Greenewable Energy for 100MW of embedded generation.

The company said it was working on further arrangements with Capstone Energies for 50MW and North South Power for 17MW of distributed embedded supply. It is also exploring more than 420MW in potential embedded generation, distributed power and interconnected mini-grid opportunities.

These figures should not be added together as if they were all secured supply. A memorandum of understanding is not a commissioned power plant, and a power-purchase agreement under negotiation is not a completed supply contract. The reports do not explain the precise overlap between the 205MW pipeline and the individual proposals.

Mwenendo has previously examined why Kenya's proposed 500MW power project needs competitive procurement. The same distinction matters here: planned capacity and announced partnerships must be tested against signed contracts, construction and actual electricity delivered.

Embedded generation can feed power directly into a local distribution network, reducing reliance on long-distance transmission for the customers it serves. But the plants still need financing, construction, fuel or renewable-energy resources, grid connections and contracts before electricity reaches users.

The regulator's role

The Anambra State Electricity Market Investment Roundtable was organised by the Anambra State Electricity Regulatory Commission, which oversees the state's electricity market. The regulator's 2026 investment regulations set out a framework intended to facilitate private investment in generation, transmission, distribution and electricity trading.

That framework will matter as FirstPower seeks partners and develops its supply pipeline. The regulator will need to monitor licensing, technical standards, consumer protection and the terms under which new capacity is connected to the distribution network.

The key issue for customers is not simply how much investment is announced. It is whether projects are funded, completed on schedule, connected safely and reflected in more reliable service.

What businesses should watch

The first milestone is the delivery of the 2027 network investment programme. Businesses should look for disclosed project locations, contract awards, equipment installation and the commissioning of upgraded substations and feeders.

The second is the conversion of supply proposals into binding agreements and operating plants. The 100MW Greenewable project, the 55MW procurement talks and the proposed 50MW and 17MW arrangements need clear financing, construction and commissioning milestones.

The third is measurable service improvement. Better metering, fewer interruptions and more predictable supply would help companies plan production and reduce dependence on backup power. FirstPower has not yet published a timetable showing when customers in specific areas should expect those improvements.

Image note: The cover is an AI-generated contextual illustration and does not depict a specific FirstPower project.

#FirstPower
#Anambra
#Electricity Distribution
#Energy
#Nigeria
#EEDC
#Embedded Generation

In Summary

How much does FirstPower plan to invest?
₦53.3 billion between 2027 and 2029, equivalent to about KSh5.07 billion or US$39 million using the reported figures.
When is the investment scheduled?
The company outlined ₦13.3 billion for 2027 and another ₦40 billion across 2028 and 2029.
Which electricity market is covered?
Anambra State in south-eastern Nigeria, where FirstPower is the licensed electricity distributor.
Are the proposed megawatts already available?
No. The reported generation proposals, MoUs and power-purchase discussions remain at different stages and are not all commissioned supply.
AI images used for illustration purposes. All news and stories are factual.
KSh65B for African Businesses: IFC Announces 14 New Projects

Up next

african-business

KSh65B for African Businesses: IFC Announces 14 New Projects

The International Finance Corporation announced more than KSh64.98B (US$500M) in 14 new African projects on 16 November.

Read next story

More from african-business

See all

Latest from Mwenendo