A KSh43.94 Billion Exit Sum: Treasury's Adani Estimate Tops Line CostsA KSh43.94 Billion Exit Sum: Treasury's Adani Estimate Tops Line Costs
Key Highlights
- Treasury's latest report puts the estimated exit sum for two cancelled Adani power lines at KSh43.943 billion.
- The figure is KSh3.453 billion above the KSh40.490 billion project amount listed for the transmission lines.
- The report treats the sum as a contingent exposure, not confirmation that the government has paid or owes it now.
Dek: The National Treasury puts the estimated termination sum for two KETRACO power-line projects at KSh43.943 billion, above their listed project amount of KSh40.490 billion. The figure is a contingent exposure, not proof of a payment already due.
Kenya's estimated cost of ending the cancelled Adani transmission-line agreements stands at KSh43.943 billion, according to the National Treasury's Annual Public Debt Management Report for the 2025/26 financial year.
The Treasury's Annual Public Debt Management Report lists the amount as the termination sum for the 400-kilovolt Lessos-Loosuk line and the 220-kilovolt Kisumu (Kibos)-Kakamega-Musaga line. It places the projects' combined amount at KSh40.4898 billion and their estimated termination sum at KSh43.943 billion.
The difference is KSh3.4532 billion, meaning the estimated exit sum is about 8.5 per cent higher than the amount listed for the two projects.
The figures provide a primary-source basis for the KSh43.94 billion estimate that has circulated in recent secondary reports. The Treasury's Fifth Annual Report on the State of Public-Private Partnerships also lists the same termination sum and says the KETRACO-Adani termination process was still ongoing at the end of June 2026.
What the KSh43.943 billion covers
The Treasury table identifies the contracting authority as the Kenya Electricity Transmission Company (KETRACO), the project stage as commercial close, the project amount as KSh40,489.8 million and the estimated termination sum as KSh43,943 million.
The estimate relates to the two named transmission-line PPPs. It should not be confused with the wider Adani power infrastructure proposal, which was described in other public records as including additional transmission infrastructure and substations.
The Treasury's PPP report says the termination process for the contract between KETRACO and Adani began in the 2024/25 financial year and remained in progress at the end of FY2025/26. That means the presidential announcement that the project would be cancelled in November 2024 did not, by itself, complete the contractual separation.
The reports establish an estimated termination sum. They do not show that KSh43.943 billion has been paid, that the full amount has been accepted by KETRACO or that a final settlement has been agreed.
An estimate is not an invoice
The Treasury classifies termination payments under public-private partnerships as contingent liabilities. In plain language, these are possible future financial obligations that may arise if specified events occur under a contract. Their timing and final value depend on the terms of the agreement and the facts established during the termination process.
The PPP Directorate's report cautions that the likelihood, value and timing of termination payments cannot be determined with certainty in advance. It also says that multiple projects are unlikely to be terminated at the same time, so their combined estimated sums should not be treated as a bill falling due immediately.
That qualification is central to interpreting the Adani figure. KSh43.943 billion is the Treasury's estimate in its termination-payment table as at June 2026. It is not a confirmation of the amount that taxpayers will ultimately pay.
The same PPP report says the termination of the KETRACO agreement was still ongoing at the end of the financial year. It does not provide a detailed public breakdown in the table of the costs claimed by Adani, the amounts verified by KETRACO, or the basis on which the estimate was calculated.
Why the estimate is above the project amount
A termination sum and a project amount measure different things. The project amount is the value listed for the planned infrastructure. A termination estimate can reflect contractual costs or liabilities that arise when an agreement is ended before the planned works and operating period are completed.
The public reports available do not provide enough detail to determine which individual cost components account for the KSh3.4532 billion difference. It would therefore be premature to describe the gap as a penalty, compensation already approved or money owed to Adani.
The key documents needed to explain the estimate are the relevant termination clauses, KETRACO's cost verification, any claims submitted by Adani Energy Solutions, the independent technical or financial assessments and the final mutual-separation agreement, if one has been reached.
The records still needed
KETRACO and the Treasury need to clarify whether the termination process has been concluded since the 30 June 2026 reporting cut-off, what costs have been verified and whether any amount has been paid or formally accepted.
The government also needs to explain how the two transmission lines will be financed and delivered after the Adani agreement ends. The lines were intended to add capacity to Kenya's electricity network, so any replacement plan matters for power reliability, the movement of electricity from generation sites and the cost of building the network.
For now, the documented position is specific: Treasury recorded a KSh43.943 billion estimated termination sum against a KSh40.4898 billion project amount for the two KETRACO transmission-line PPPs. The final settlement remains a separate question.
The fiscal implications sit alongside Kenya's broader borrowing pressures. Mwenendo has examined the country's debt burden and borrowing plan, including the distinction between debt measures and annual financing plans.
In Summary
- What termination sum did Treasury list?
- KSh43.943 billion for the 400kV Lessos-Loosuk and 220kV Kisumu (Kibos)-Kakamega-Musaga transmission-line PPPs.
- How does it compare with the listed project amount?
- The listed amount is KSh40.4898 billion, making the estimated termination sum KSh3.4532 billion higher.
- As at what date was the estimate reported?
- The Treasury's termination-payment table gives the estimate as at June 2026.
- Does this mean the government has paid KSh43.943 billion?
- No. The report treats the figure as an estimated termination sum and says the timing and final value of such payments are uncertain.