A KSh30.73 Million Question: Senator Presses for Answers on Marsabit's Loiyangalani Fish Factory

Key Highlights

  • A Senate request puts a long-delayed Marsabit fisheries project back under scrutiny after auditors found it less than half complete.
  • The Auditor-General recorded KSh30.73 million paid against a KSh34.81 million contract, with supporting documents missing for KSh26.01 million.
  • Marsabit's own development plan later said the factory and two cold rooms were submerged as Lake Turkana rose.

Kenya's Senate is being asked to explain the Loiyangalani fish factory in Marsabit County, which the Auditor-General found in September 2022 was still below 50 per cent complete even though payments had reached 88 per cent of its contract sum.

AI-generated illustration of Lake Turkana fishers unloading catch beside a fish-processing and cold-chain facility

The audit recorded KSh30.73 million paid against a KSh34.81 million contract. It also said supporting documents had not been provided for KSh26.01 million of the payments, leaving the Auditor-General unable to confirm value for money.

The request is listed on the Senate's 19 November 2026 Order Paper. The Marsabit senator, Mohamed Chute, is scheduled to seek a statement from the Senate Standing Committee on Agriculture, Livestock and Fisheries on the factory's construction, financing and operationalisation.

The Order Paper records a request for answers, not a response from the county or the national government.

What the 2022 audit found

The Auditor-General's report on the County Executive of Marsabit for the year ended 30 June 2022 says the county contracted a company in January 2018 to construct the fish factory at a cost of KSh34,811,743. The contract period was 63 weeks. Work began on 12 January 2019 and was due for completion on 25 June 2020.

A physical inspection in September 2022 found the project below 50 per cent complete, although KSh30,734,551, or 88 per cent of the original contract sum, had been paid.

The report identified three payments totalling KSh26,012,216 for which supporting documents were not provided: KSh12,121,216 relating to certificate number three, KSh11.3 million for prime cost and contingencies, and KSh2.6 million for project management expenses.

The audit also said documents supporting a KSh2,225,407 contract variation, which would have raised the contract sum to KSh37,037,150, and its approval were not provided. The report said it was unclear when the project would be completed and that value for money on the KSh30.73 million expenditure could not be confirmed.

Those are serious accountability findings, but they are not a finding that money was stolen or that fraud occurred. The audit's stated concern was that the county had not supplied the records needed to verify the payments, the variation and the value of work completed.

The county later said the factory was submerged

Marsabit County's Annual Development Plan for 2025/26 provides a later account of fisheries infrastructure. In its review of 2023/24 achievements, the county says rehabilitation of two cold rooms, a dry-fish store at Moite, an ultra-modern fish-processing factory and solar-powered cold-chain facilities had been undertaken.

It then states that the two cold rooms and the factory were all submerged. The plan does not identify the 2018 contract by number, so the precise link between the audited contract and the submerged facility should still be confirmed.

The plan also reports fish production of 400 tonnes against a target of 100 tonnes and says 2,885 fisherfolk had received training. Those are county-reported achievements. The document does not set out the operating status of the submerged factory, how much fish passed through its cold rooms, or whether replacement facilities had been completed.

A Kenya News Agency report published on 18 July 2026 quoted Marsabit county officials saying rising Lake Turkana waters had submerged fishing infrastructure and disrupted livelihoods in Loiyangalani.

County Secretary Dr Halkano Arero said a new site on higher ground had been identified and that the county had signed a memorandum of understanding with World Vision Kenya. He said the county was exploring ways to revive affected fish cold-chain facilities.

The report also quoted Arero saying KSh7 million had been allocated in the 2026/27 county budget to support fisherfolk whose boats and fishing gear were damaged. An allocation is not evidence that the money has been released or that all affected households have received support.

The county officials' account helps explain why the factory's status matters beyond the original construction contract. Cold storage and processing facilities allow fishers to preserve fresh catch, reduce spoilage and reach buyers beyond the immediate lakeshore. When the cold chain is lost, producers can be pushed towards lower-value sales or face higher transport and storage costs.

What the Senate needs to establish

The statement request gives the committee an opportunity to connect the 2022 audit to the later reports of flooding and relocation. It should establish whether the facility inspected by the Auditor-General is the same factory the county later described as submerged, and whether the original contract was completed, abandoned, relocated or replaced.

The county and relevant national agencies should provide the original contract, payment certificates, inspection and completion records, the variation approval, the handover documents and any later asset register entry. They should also identify the source of financing, the contractor's obligations, any insurance or climate-loss claims, and the amount spent on repairs or replacement.

The current status of the proposed higher-ground site also needs to be documented. A site identified or a memorandum signed is not the same as land acquired, a project funded, construction started or a working cold-chain facility opened. The county should publish a timetable, budget, responsible agency and measurable operating targets.

The county's public projects page does not provide a current project-level update on the Loiyangalani factory. That absence does not establish that no work has taken place, but it makes a detailed response to the Senate request more important.

The economic cost of a missing cold chain

The factory is part of a wider fisheries economy around Lake Turkana. Fish processing, ice, cold storage, transport and reliable market access determine how much value local fishing communities can retain from each catch.

KNA reported in July that about 200 households in Loiyangalani had been displaced by rising lake waters and quoted county officials estimating losses above KSh300 million across affected communities. That estimate covered wider climate-related damage and should not be attributed to the fish factory alone.

The county's plans for a higher site and renewed cold-chain facilities could help restore market access, but the public record still needs to show what has been funded and delivered. The issue is relevant to the county's own-source revenue as well as fisherfolk incomes, food supply and private traders who depend on predictable volumes and quality.

Mwenendo has also examined the national financing and delivery challenge in Ruto's State of the Nation address and the pressure created by Kenya's rising public debt. The Loiyangalani case brings that broader question down to a specific public asset: what was paid, what was built, what was lost and what residents can use today.

The Senate's requested statement should provide the missing link between the original contract, the audit findings and the county's later account of submerged facilities. Until those records are tabled, the factory's present operating status and the final value delivered by the KSh30.73 million paid remain unresolved.

Image note: The cover image is AI-generated for illustration and does not depict the actual Loiyangalani facility.

#Marsabit
#Loiyangalani
#Lake Turkana
#fisheries
#county audit
#fish processing
#cold chain
#public finance

In Summary

Who is seeking answers?
Marsabit Senator Mohamed Chute is scheduled to seek a statement from the Senate Agriculture, Livestock and Fisheries Committee.
What is under scrutiny?
The construction, financing and operationalisation of the Loiyangalani fish factory, including KSh30.73 million paid under the original contract.
When did the audit find delays?
A physical inspection in September 2022 found the project below 50 per cent complete.
Where is the project?
Loiyangalani, Marsabit County, on the eastern shore of Lake Turkana.
Why does the project matter?
Fish processing and cold storage reduce spoilage and help fishing communities reach higher-value markets.
What is still unknown?
The Senate needs current records on completion, payments, the submerged facilities, relocation plans and whether a replacement cold chain is operating.
AI images used for illustration purposes. All news and stories are factual.
Tax Relief Proposed: Ruto's State of the Nation Sets Out a KSh5 Trillion Plan

Up next

african-economy

Tax Relief Proposed: Ruto's State of the Nation Sets Out a KSh5 Trillion Plan

Ruto's address proposed tax relief and a KSh5 trillion investment plan, but the legal changes still need a timetable.

Read next story

More from african-economy

See all

Latest from Mwenendo